Overview
Once all required prior steps are complete, the project is ready to be scheduled for installation. The ESP Installation Scheduling team will coordinate with the homeowner to arrange the installation date. While it is not required the homeowner is home on installation day, it is highly recommended. Generally, the installation will be scheduled about a week ahead, though the exact timeframe may vary depending on the location of the project. The homeowner will receive a notification once the installation date is set.
If the homeowner has any questions prior to the installation date, they can reach out to the ESP project Management team via call or chat.
The scope of work will involve the installation of solar panels, inverters, and batteries, if applicable. Typically, the installation process can be completed within a day, but larger systems may require additional time. If a battery is included in the project, an extra day will be needed.